Last year, TOB New Energy signed a contract for a cylindrical battery production line with a factory, after communication and planning of the project by both parties, the equipment is currently being prepared in an order, many devices have entered the assembly stage.
Battery and Materials Baking oven
200L Vacuum planetary mixer
High precision lithium battery electrode rolling machine
18650 Cells Assembly Line
Automatic Electrolyte Filling System
Battery Safety Testing Equipment
Battery capacity, cycle, performance tester
Formation and grading machine
Nitrogen making machine
All equipment is expected to be delivered in June. After the equipment arrives at the customer's factory, our team of engineers will go to the customer's factory to help the installation and commissioning of the equipment, and conduct pre-job training, the project will run soon!
Contact person:Gavin Zhu (Engineer & Sales)
Email:tob.gavin@tobmachine.com
Skype: tob.gavin@tobmachine.com
Wechat: TOB-007